Laie Elementary School |
Cafeteria Expansion & Renovation / painting |
Cafeteria
Expansion |
||
| September 2002 - August 2003 | Expanded
and upgraded existing Cafeteria. Work included: Selective Demolition &
Removal; Sitework: Asphalt parking lot & Fencing, Landscaping, Concrete
& CMU, Roofing, Drywall/Acoustic Ceiling, Ceramic Tile, Flooring,
Exterior/Interior Painting, Plumbing/Septic Tank, Greasetrap, and Electrical/Fire
Alarm. |
$1,023,180 |
|
Renovation
& Painting
|
||
| March - August 2002 | Renovated
& Painted all buildings. Work included: Remove/Re-install school equipment,
ACM/LBP removal, Remove/Replace Cabinetry, Tackboard/Whiteboard, Termite-damaged
Wood, Windows/Doors, Signage, Finish hardware, Roofing, Drywall, Interior/Exterior
Painting, Flooring, Plumbing, and Electrical work. |
$1,137,749 |