Laie Elementary School

Cafeteria Expansion & Renovation / painting

 

Cafeteria Expansion
 September 2002 - August 2003
Expanded and upgraded existing Cafeteria. Work included: Selective Demolition & Removal; Sitework: Asphalt parking lot & Fencing, Landscaping, Concrete & CMU, Roofing, Drywall/Acoustic Ceiling, Ceramic Tile, Flooring, Exterior/Interior Painting, Plumbing/Septic Tank, Greasetrap, and Electrical/Fire Alarm.
 $1,023,180
Renovation & Painting
March - August 2002
Renovated & Painted all buildings. Work included: Remove/Re-install school equipment, ACM/LBP removal, Remove/Replace Cabinetry, Tackboard/Whiteboard, Termite-damaged Wood, Windows/Doors, Signage, Finish hardware, Roofing, Drywall, Interior/Exterior Painting, Flooring, Plumbing, and Electrical work.